Dear Team,
We are upgrading our current QAS CRM 7.0 System to EHP3 for CRM 7.0
SAP Application.
In Downtime (Execution Phase )
Job Job MAIN_SWITCH/SUBMOD_SWITCH_OLDREL/JOB_BTCTRNS1 running from very long time now.(Almost 5 Hrs)
I can see below errors in dev_w0 files in DVEB*/works directory:-
Mon Jul 14 22:45:40 2014
M ***LOG Q0I=> NiPConnect: 172.16.1.4:51019: connect (239: Connection refused)
M *** ERROR => NiPConnect: SiConnect failed for hdl 8/sock 17
(SI_ECONN_REFUSE/239; I4; ST; 172.16.1.4:51019)
M {root-id=00215A0DE2E91EE482EC5531B64F9C04}_{conn-id=00000000000000000000000000000000}_0
M *** ERROR => EncNiConnect: unable to connect (NIECONN_REFUSED)
M {root-id=00215A0DE2E91EE482EC5531B64F9C04}_{conn-id=00000000000000000000000000000000}_0
Can not see any recent logs (logs not getting generated) in SUM/abap/log.
Please help
regards,
Alok