Hello Experts,
Today in our Production system, one of the work process has reached 14GB which is surprising.
I couldnt even restart that particulat work process from SM50 as a job is running.
Once the job finished it has moved to ".old" i.e. - dev_w9.old, then i moved to some other directory by which i am able to get some free space
I am still not able to understand how come the file has grown to 14GB though i have the following parameters set:
rdisp/TRACE = 1 (Explanation - 1 Error messages are written to the trace file)
rdisp/TRACE_LOGGING = on, 50 m (Explanation - Trace logging if trace file is larger than 50 MB)
rdisp/autothtime = 60
Could you please let me know of i need to set any more paremeters to restrict the growth of the developer trace file
Thanks,
Subbu