Hello Team,
We are currently progressing with our upgrade. As of now we have finished all the non-production systems and final cutover is in weeks’ time.
I have a question related to transport routes.
The transport domain controller is configured in development system and then later we have added Integration system and regression system. As part of the final cutover we will add production system in the route (Delivery route). So after final cutover if we look the track will be
- DEV(TDC) à INT à REG à PRD
Now the question is following, when we add a delivery route to PRD from REG will all the transports get added to target system (PRD) buffer automatically?
If yes, how will the sequence be, the same way it did import in previous system (REG)?
(As far as am aware the answer is yes)
It will be highly appreciated if you can also route to SAP notes or SAP documents.
Many Thanks
Praveen Kumar