I have performed the following, during a heterogeneous system copy.
On the source system:
1. Check that there is no active job.
2. Run btctrns1
On the destination system:
3. Set the number of background job to zero
4. Modify selected jobs status, in sm37:released/susp. -> scheduled so that they do not start
5. Stop SAP
6. Start SAP with several background processes configured.
7. Run btctrns2
After running btctrns2, a few jobs became active although they had been changed to scheduled.
From my understanding, they should not have been started.
Could you explain why these "non released jobs" had been started by SAP?