Hi Experts,
Am planning to do system copy in ECC system from PRD to QUA.My ECC system Quality system SID:QUA Clnt:600
Production SID:PRD Clnt:900
If I do system copy ( Prd-->Qua ) by Back-up/Restore method,Once System copy is completed what will be in Qua?
1)Does Qua system overwrite by PRD or replace PRD content?
2)What are the clients will be in Qua after system copy?
Before System Copy in Qua:Clnt 600
After System copy:what are clients will be there?
3)Do we need to run BDLS after installing SAP license ( mean before changing Client config in SCC4)?