According the SUM part of JAVA in phase Configuration "show validation results" I get an error.
According to the error the system has a higher level than the one in the stack xml file. But when I generated a new stack XML and used that it still runs in the same error.
I cannot skip nor continue as in this phase it comes that I need to provide a password given by SAP to be able to go on with the update.
message is:
Validation of deployment queue completed with error: The stack does not match the system. Probably the system was changed after the stack was generated. Synchronize the system with SAP Solution Manager and then generate a new stack. Software component sap.com/BI-BASE-B with version 7.30.10.20 is found on the system but in the stack it is listed with version 7.30.9.40. Software component sap.com/BI-BASE-S with version 7.30.10.20 is found on the system but in the stack it is listed with version 7.30.9.40. Software component sap.com/BI-IBC with version 7.30.10.20 is found on the system but in the stack it is listed with version 7.30.9.40. There are 2 more error messages. See them all in /oracle/CBO/SUM/sdt/log/SUM/CHECK-QUEUE_03.LOG.
I created a stack file for stack 11