Dear Experts,
Am stuck in the upgrade NTACT_ALTNT phase of the EHP7 upgrade
Source: SAP ECC6.0
Target: SAP ECC 6.0 EHP7
In the preprocessing phase got an error in the MAIN_SHDIMP/SUBMOD_SHD2_RUN/NTACT_ALTNT phase. Please find the logs below.
ANTCPINT and RETURN CODE in PN810331.EV0
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
3 ETP399Xcopy nt "CNVCHECKPROFILES":
3 ETP399 done. (T/F Src: T/T)
3 ETP399Xcopy nt "CNVCHECKTMPDUPL":
3 ETP399 done. (T/F Src: T/T)
3 ETP399Xcopy nt "CNVCLU":
2EETP399XRead table "CNVCLU ": pgntab call: table not found.
2AETP399 Table "CNVCLU": unknown error -9
3 ETP399Xcopy nt "CNV_00001_SIMMON":
3 ETP399 done. (T/F Src: T/T)
3 ETP399Xcopy nt "CNV_00001_STATUS":
3 ETP399 done. (T/F Src: T/T)
3 ETP399Xcopy nt "CNV_00001_USR":
2EETP399XRead table "CNV_00001_USR ": pgntab call: table not found.
2AETP399 Table "CNV_00001_USR": unknown error -9
1 ETP111 exit code : "12"
When i checked the tables CNVCLU and CNV_00001_USR in actual instance 000 client. Am able to see the table in SE14 in NOT ACTIVE state. However in SE11 it showed table doesnt exist.
Already check the note 719989 - SLO: Deleting data from CNVCLU after conversion but am unable to delete the same. All the fields in the SE14 is inactive.
Please let me know to resolve this issue.